Skip to content
Saudi Commercial Papers Law · Cheque

Article 109: Deadline for recording non-payment

Non-payment must be recorded, in the way set out in article 108, before the presentation period ends; if the cheque was presented on the last day of that period, it may be recorded on the next working day.

What it means in practice

  • The presentation periods are those in article 103; missing the deadline for recording non-payment affects the holder’s rights against the drawer and endorsers under article 115.

The official text

Arabic (the authoritative text)

يجب إثبات الامتناع عن الدفع بالكيفية المنصوص عليها في المادة السابقة قبل انقضاء مواعيد التقديم، فإذا وقع التقديم في آخر يوم من هذا الميعاد جاز إثبات الامتناع عن الدفع في يوم العمل التالي. ​

The Ministry of Commerce’s English translation

Failure to pay must be proved in the manner provided for in the preceding article before the expiry of the submission deadline. If the submission is made on the last day of such date, the failure may be proved on the following working day.

The text as the Ministry of Commerce publishes it on its laws and regulations platform. The explanation above is for guidance, not legal advice; the Arabic text is the one that governs.

Related articles

Bills of exchange, promissory notes and cheques

Sources

  1. نظام الأوراق التجارية — وزارة التجارة
  2. Commercial Papers Law — Ministry of Commerce

Checked on: 5 November 2026. The explanation is written from the article’s text alone, for guidance; it is not legal advice.