Article 12: Review of the application and preliminary approval
Under the recruitment rules, a licence application must meet every requirement or it is void. The Ministry studies it and may ask for more, grant a preliminary approval to establish the company, or refuse it with reasons.
What it means in practice
- The Ministry may ask for further documents or for the applicant’s representative to attend and answer questions. If the documents are not provided or the representative does not attend within 30 days of notice, the application is void.
- If approved, the applicant gets a preliminary approval to establish the company for no more than 180 days, and then applies for the final licence once the conditions are complete. The activity may not start before the licence is obtained.
- If the Ministry refuses the application, the refusal must state its reasons.
The official text
1. يجب أن يستوفي طلب الترخيص جميع المتطلبات المنصوص عليها في هذه القواعد، وفي حالة عدم استيفاء الطلب لكامل المتطلبات يعتبر الطلب لاغياً.
2. تتولى الوزارة دراسة الطلب، ولها أن تتخذ أياً من الإجراءات الآتية:
أ. طلب أي وثائق إضافية أو مستندات أخرى، أو أن تطلب حضور من يمثل مقدم الطلب إلى الوزارة للإجابة عن أي استفسار، أو لتوضيح أي مسألة تتعلق بطلب الموافقة على الترخيص، وإذا لم يتم تقديم الوثائق أو المستندات أو لم يحضر ممثل مقدم الطلب خلال ثلاثين (30 ) يومًا من تاريخ إبلاغه اعتبر الطلب لاغياً.
ب. تتم دراسة الطلب من قبل الوزارة وفي حال الموافقة ويمنح المتقدم الموافقة المبدئية للتأسيس بفترة لا تتجاوز (180 ) يوم، على أن يتقدم بالحصول على الترخيص النهائي بعد استكمال الاشتراطات.
ج. إشعار مقدم الطلب بالموافقة المبدئية عند اكتمال طلبه بعد استيفاء جميع المتطلبات المنصوص عليها في القواعد. ولا يجوز البدء في ممارسة نشاط الاستقدام وتقديم الخدمات العمالية إلا بعد الحصول على الترخيص.
د.
رفض الطلب بشرط أن يكون مسببًا.
The Arabic text as the Ministry of Human Resources and Social Development publishes it in “The Implementing Regulations of the Labor Law and their annexes”; the Ministry publishes no English translation of it. The explanation above is for guidance, not legal advice.
Related articles
- Article 5: One-year wait after a refused applicationUnder the recruitment rules, an applicant whose application was refused may not file a new licence application until one year has passed from the date of refusal.
- Article 7: Issuing the licence and checking requirementsUnder the recruitment rules, the Ministry issues the licence once the applicant has met all conditions and procedures, including providing human resources and systems and the equipment needed to start, and the agency may verify this by any means.
- Article 10: Requirements for preliminary approvalUnder the recruitment rules, this article lists the documents and conditions required with a licence application to obtain preliminary approval, including partners’ fitness conditions, a detailed business plan, an initial bank guarantee and extra documents for a foreign investor.
- Article 14: Requirements for the final licenceUnder the recruitment rules, this article sets what is needed after preliminary approval to obtain the final licence: notifying the agency to schedule a licensing visit, then meeting the conditions on capital, guarantee, housing, premises, electronic systems and call centres.
Sources
- اللائحة التنفيذية لنظام العمل وملحقاتها — الملحق رقم (4): قواعد ممارسة نشاط الاستقدام وتقديم الخدمات العمالية — وزارة الموارد البشرية والتنمية الاجتماعية
Checked on: 5 November 2026. The explanation is written from the article’s text alone, for guidance; it is not legal advice.